22/08/2025

How do you fix setup violations? What if upsizing/layer change isn't possible?

o   We need to reduce cell delay or Net delay or use more skew – can use various methods for each.

o   Reduce Cell Delay:

o   Cell Sizing (Upsizing): Increase drive strength of cells on the critical path. (Effective for small to moderate violations).

o   VT Swapping (Lowering Vt): Swap cells to faster, lower-Vt variants (HVT->SVT->LVT). (Effective, but increases leakage).

o   Reduce amount of buffering if excessive bufs are added.

o   Reduce Net Delay:

o   Buffer Insertion: Insert buffers to break long nets or strengthen signals. (Good for net-delay dominated paths).

o   Replace buffer with two inverters and reduce net length.

o   Adjust cell position, keeping cell at middle of the net gives less net delay.

o   Routing Optimization: Re-route critical nets on faster layers or using shorter paths. (Limited impact usually, but possible).

o   Useful Skew: Delay the capture clock or speed up the launch clock path intentionally. (Requires careful analysis of side effects).

 

  • Fixing Different Violation Magnitudes:
    • Small Violations (e.g., 5ps, 20ps): Often fixed by minor sizing changes (e.g., X2->X3), VT swaps on a few cells, or small useful skew adjustments.
    • Moderate Violations (e.g., 300ps): May require more aggressive sizing (e.g., X1->X4), multiple VT swaps, buffer insertions, or significant useful skew. Logic restructuring might be needed. Placement is key.
    • Large Violations (e.g., 500ps, 1ns): Indicate more fundamental issues. Simple sizing/VT swaps are unlikely to be sufficient. More likely constraint issues or missing MCP or pipelining.
Fixing Setup/Hold: https://www.vlsi-expert.com/2014/01/10-ways-to-fix-setup-and-hold-violation.html