o Reg2Reg WNS/TNS:
o Acceptable:
A small negative WNS (e.g., -50ps to -200ps for a multi-GHz design, perhaps
-10% to -20% of the clock period) might be considered acceptable as a starting
point for PnR. TNS should ideally be manageable.
o Context:
The acceptable value depends on how much improvement is expected from PnR
optimizations (better placement, buffering, useful skew, more accurate
parasitics).
o
Extremely High Negative WNS/TNS: If the
WNS is very large negative (e.g., approaching or exceeding the clock period) or
TNS is enormous:
o Unrealistic
Constraints: Clock frequency target is too high for the
technology/architecture. SDC constraints (I/O delays, exceptions) might be
incorrect or too tight.
o Poor
RTL Quality: Inefficient logic structure, very long combinational paths,
complex computations within a single cycle.
o Incorrect
Libraries: Using the wrong speed/Vt libraries for synthesis.
o Synthesis
Tool Issues: Incorrect settings, poor optimization effort.
o Action:
The issue must be investigated and addressed in synthesis (fixing constraints,
guiding the tool, requesting RTL changes)
o
ICG WNS (Integrated Clock Gating):
o Target:
ICG setup timing (WNS) should ideally be positive or very close to zero
after synthesis. Clock gating checks are often harder to fix post-synthesis
compared to regular reg-to-reg paths.
o Negative
ICG WNS: If ICG setup WNS is significantly negative, it's a concern. It
implies the enable logic path is too slow. This should be prioritized for
fixing during synthesis, potentially by:
§ Optimizing
the enable logic path.
§ Adjusting
clock gating insertion strategy.
§ Using faster cells for the enable logic or the ICG cell itself.